Movement Joints and Installation Detail
The joint below the masonry relieving angle incorporates compressible filler and mastic pointing to allow for a weather proof gap of sufficient size to allow for:
- expansion of the masonry panel below
- any shrinkage or deflection of the building’s supporting structure
- allowable settling of the masonry support angle.
The minimum gap should be at least 12mm between bricks where there is a single storey height of brickwork below the support system. The gap should be increased by 1mm for every additional metre in panel height.
Installation
Detail:

References:
a)
Waterproof pointing detail (mastic) b)
Compressible backing rod
Heel Support
Support at the heel of the bracket is a critical consideration when designing bracket/angle systems, as failure to support the heel correctly could result in unacceptable deflection at the toe of the angle.
Our standard bracket is designed to be shorter in height than competing products. This maximises the chances of adequate heel support being achieved with a standard bracket, and minimises the chances of specials having to be designed and manufactured.
Good Heel Support Bad Heel Support
Registered in Ireland # 281833
Riverside, Tullamore,
County Offaly, Republic of Ireland
Telephone enquiries between 08.30 and 17.30 GMT
Outside of hours enquiries should be directed to an agent in your area
Web Design Ireland by Martec